Prince William Street Project

Project update

July 16, 2018: Temporary waterline is being installed above ground between Jefferson Street and Grant Avenue.  This temporary waterline will be put into service later this week.  Excavations for the water line lining portion of the project will begin on Wednesday, July 18, 2018.  

Important Note:  You may experience brief interruptions of water service while we connect your water service to the temporary by-pass water piping the following two days.

Water line
Our Public Works team met with the community at City Hall to discuss the Prince William Street project.  Staff presented information on the project and solicited feedback.  Links to this information are shared below.  All documents are in PDF format.
 

Project Status:

 

Underground Electric, Comcast and Verizon – completed

Columbia Gas work – completed

Advertised for construction – December 12, 2017

Bids received – February 9, 2018

Award Project – June 2018

Begin Construction – July 2018
Contractor - Fort Myer Construction and Utility Services Company

Project Complete – Spring 2019   


Informational Resources:


Pre-Construction Citizens Presentation (June 20, 2018)
Pre-construction Update to residents (letter June 8, 2018)
Prince William Street May 11th Meeting  (letter to residents)
Typical Section 36X24 one side sidewalk left
Typical Section 26X24
Prince William Street Aerial Outfall  (Note: very large PDF = 32MB)
Prince William Street Roadway Plan
Prince William Street Water and Sewer Plan
Prince William Street Aerial  (Note: very large PDF = 46 MB) 
Public Meeting Presentation Slideshow
Fact Sheet

City Staff:


Michelle Brickner, City Engineer:  703-257-8251
Corinna Sigsbury, Senior Engineer:  703-257-8397